Manta Bay Construction Update Q1, 2026

Phase 1 - Enabling Works (100% Completed)

  • Soil investigation and topographical survey completed
  • Site mobilization and setup fully completed
  • All enabling activities completed
  • Dewatering works completed
  • Piling works complete

Phase 2 - Main Work Stream (In Progress)

  • Foundation works completed

  • Substructure waterproofing works completed
  • Raft floor and pile caps completed
  • Basement columns completed
  • Ground floor slab works progressing 90% completed
  • Ground floor columns underway, currently 50% completed
  • Mezzanine and swimming pool floor works commenced
  • Initial MEP wor commenced.