Manta Bay Construction Update Q1, 2025

  • Project site mobilization was completed.
  • Soil Investigations were done.
  • Soil Improvement was completed.
  • Shoring system was done.
  • Dewatering work was done.
  • Excavation works were done.
  • Piling work is in progress on the site.
  • The expected date of completion for the full enabling works is 20th May 2025.
  • The tendering stage was done and the negotiation with the main contractor is in progress.

    Manta Bay Construction Update Q1, 2026

    Phase 1 - Enabling Works (100% Completed)

    • Soil investigation and topographical survey completed
    • Site mobilization and setup fully completed
    • All enabling activities completed
    • Dewatering works completed
    • Piling works complete

    Phase 2 - Main Work Stream (In Progress)

    • Foundation works completed

    • Substructure waterproofing works completed
    • Raft floor and pile caps completed
    • Basement columns completed
    • Ground floor slab works progressing 90% completed
    • Ground floor columns underway, currently 50% completed
    • Mezzanine and swimming pool floor works commenced
    • Initial MEP wor commenced.