Manta Bay

Manta Bay Construction Update Q1, 2026

Phase 1 – Enabling Works (100% Completed) Phase 2 – Main Work Stream (In Progress)

Manta Bay

Manta Bay Construction Update Q4, 2025

Phase 1 – Enabling Works (100% Completed) Phase 2 – Main Work Stream (In Progress) Phase 3 – Services & Systems (Initiated)

Manta Bay

Manta Bay Construction Update Q3, 2025

Phase 1 – Enabling Works (100% Completed) Phase 2 – Main Work Stream (In Progress) Site housekeeping and safety preparations are ongoing

Manta Bay

Manta Bay Construction Update Q2, 2025

Phase 1- Enabling Package (G5% was done) Final formation leveling in progressThe expected date of completion for the full package of enabling work is 30th May 2025. Phase 2- Main Package- Main Contractor (In Progress)

Manta Bay

Thank you

Thank you for your enquiry. A member of our sales team will be in contact with you shortly.

Thank you

Thank you for your enquiry. A member of our business development team will be in contact with you shortly to discuss and explore potential avenues for collaboration.

Manta Bay Construction Update Q1, 2026

Phase 1 - Enabling Works (100% Completed)

  • Soil investigation and topographical survey completed
  • Site mobilization and setup fully completed
  • All enabling activities completed
  • Dewatering works completed
  • Piling works complete

Phase 2 - Main Work Stream (In Progress)

  • Foundation works completed

  • Substructure waterproofing works completed
  • Raft floor and pile caps completed
  • Basement columns completed
  • Ground floor slab works progressing 90% completed
  • Ground floor columns underway, currently 50% completed
  • Mezzanine and swimming pool floor works commenced
  • Initial MEP wor commenced.

REGISTER YOUR INTEREST

Fill out the form below, and we will be in touch shortly.

Contact Information

Become an Agent

Fill out the form below, and we will be in touch shortly.
Contact Information