Manta Bay

Manta Bay Construction Update Q1, 2026

Phase 1 – Enabling Works (100% Completed) Phase 2 – Main Work Stream (In Progress)

Manta Bay

Manta Bay Construction Update Q4, 2025

Phase 1 – Enabling Works (100% Completed) Phase 2 – Main Work Stream (In Progress) Phase 3 – Services & Systems (Initiated)

Manta Bay

Manta Bay Construction Update Q3, 2025

Phase 1 – Enabling Works (100% Completed) Phase 2 – Main Work Stream (In Progress) Site housekeeping and safety preparations are ongoing

Manta Bay

Manta Bay Construction Update Q2, 2025

Phase 1- Enabling Package (G5% was done) Final formation leveling in progressThe expected date of completion for the full package of enabling work is 30th May 2025. Phase 2- Main Package- Main Contractor (In Progress)

Manta Bay

Manta Bay Construction Update Q1, 2026

Phase 1 - Enabling Works (100% Completed)

  • Soil investigation and topographical survey completed
  • Site mobilization and setup fully completed
  • All enabling activities completed
  • Dewatering works completed
  • Piling works complete

Phase 2 - Main Work Stream (In Progress)

  • Foundation works completed

  • Substructure waterproofing works completed
  • Raft floor and pile caps completed
  • Basement columns completed
  • Ground floor slab works progressing 90% completed
  • Ground floor columns underway, currently 50% completed
  • Mezzanine and swimming pool floor works commenced
  • Initial MEP wor commenced.