Manta Bay Construction Update Q2, 2025

Phase 1- Enabling Package (G5% was done)

  • The Project site mobilization was completed.
  • The Soil Investigations were done.
  • Soil Improvement was completed.
  • The shoring system was done.
  • The Dewatering work was done.
  • The Excavation works were done.
  • The Piling work was done successfully.
  • All tests were done.

Final formation leveling in progressThe expected date of completion for the full package of enabling work is 30th May 2025.

    Phase 2- Main Package- Main Contractor (In Progress)

    • Main Contractor (NSE) was appointed successfully.
    • The site mobilization on the site is in progress.

    Manta Bay Construction Update Q1, 2026

    Phase 1 - Enabling Works (100% Completed)

    • Soil investigation and topographical survey completed
    • Site mobilization and setup fully completed
    • All enabling activities completed
    • Dewatering works completed
    • Piling works complete

    Phase 2 - Main Work Stream (In Progress)

    • Foundation works completed

    • Substructure waterproofing works completed
    • Raft floor and pile caps completed
    • Basement columns completed
    • Ground floor slab works progressing 90% completed
    • Ground floor columns underway, currently 50% completed
    • Mezzanine and swimming pool floor works commenced
    • Initial MEP wor commenced.