Manta Bay Construction Update Q4, 2025

Phase 1 – Enabling Works (100% Completed)

  • Soil investigation and topographical survey completed
  • Site mobilization works completed
  • Enabling works completed
  • Dewatering works completed
  • Piling works completed

Phase 2 – Main Work Stream (In Progress)

  • Foundation works are 50% completed
  • Substructure waterproofing works are 90% completed

Phase 3 – Services & Systems (Initiated)

  • MEP works commenced and currently at 1% progress

Manta Bay Construction Update Q1, 2026

Phase 1 - Enabling Works (100% Completed)

  • Soil investigation and topographical survey completed
  • Site mobilization and setup fully completed
  • All enabling activities completed
  • Dewatering works completed
  • Piling works complete

Phase 2 - Main Work Stream (In Progress)

  • Foundation works completed

  • Substructure waterproofing works completed
  • Raft floor and pile caps completed
  • Basement columns completed
  • Ground floor slab works progressing 90% completed
  • Ground floor columns underway, currently 50% completed
  • Mezzanine and swimming pool floor works commenced
  • Initial MEP wor commenced.

REGISTER YOUR INTEREST

Fill out the form below, and we will be in touch shortly.

Contact Information

Become an Agent

Fill out the form below, and we will be in touch shortly.
Contact Information