Phase 1 – Enabling Works (100% Completed)
- Soil investigation and topographical survey completed
- Site mobilization and setup fully completed
- All enabling activities completed
- Dewatering works completed
- Piling works completed
Phase 2 – Main Work Stream (In Progress)
- Foundation works completed
- Substructure waterproofing works completed
- Raft floor and pile caps completed
- Basement columns completed
- Ground floor slab works progressing 90% completed
- Ground floor columns underway, currently 50% completed
- Mezzanine and swimming pool floor works commenced
- Initial MEP wor commenced.